When reducing project duration, the duration for a project that is optimal is at the point where

Chapter 9When reducing project duration, the duration for a project that is optimal is at the point whereDirect costs equal indirect costs.Total project costs are the lowest.The project changes from time-constrained to resource-constrained.Indirect costs are the lowest.Direct costs are the lowest.