AnswersRelated P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?a)9 daysb)11 daysc)17 daysd)22 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?
P : Q = 100 : 12010/12 = 20/x12/10 = x/20X = 24Q = 1/24 or 20*120/100 = 24P+Q = 1/20 + 1/24 = 24+20/480 = 44/480 = 10.91 = 11 days
Similar Quant Doubts
Question Description Solutions for P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?a)9 daysb)11 daysc)17 daysd)22 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free. Here you can find the meaning of P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?a)9 daysb)11 daysc)17 daysd)22 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?a)9 daysb)11 daysc)17 daysd)22 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?a)9 daysb)11 daysc)17 daysd)22 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?a)9 daysb)11 daysc)17 daysd)22 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?a)9 daysb)11 daysc)17 daysd)22 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Quant tests.
Exercise :: Time and Work - General Questions
Page 2
Exercise :: Time and Work - General Questions
Page 3
Exercise :: Time and Work - General Questions
Page 4
Exercise :: Time and Work - General Questions
Page 5
Exercise :: Time and Work - General Questions
|